300m3 leakage tank had 5 loosened bolts, sealing parts widely detached

Related to this article..[Photo] Rust already found inside of the contaminated water tanks [URL]

 

On 9/20/2013, Tepco released the pictures of the inside of the tank that experienced 300m3 of leakage.

From the brief inspection, they found the tank was already deteriorated significantly.

Approx. 1/3 part of the bottom plate has the sealing material detached. Also 5 bolts were found loosened.

 

↓ Loosened bolt

300m3 leakage tank had 5 loosened bolts, sealing parts widely detached

 

 

↓ Detached sealing material

2 300m3 leakage tank had 5 loosened bolts, sealing parts widely detached

 

 

↓ Detached sealing material

3 300m3 leakage tank had 5 loosened bolts, sealing parts widely detached

 

 

↓ Detached sealing material

4 300m3 leakage tank had 5 loosened bolts, sealing parts widely detached

 

↓ Rusting lateral plate

5 300m3 leakage tank had 5 loosened bolts, sealing parts widely detached

 

http://www.tepco.co.jp/nu/fukushima-np/handouts/2013/images/handouts_130920_06-j.pdf

 

 

You can ignore the truth but the truth won’t ignore you.

_____

Français :

La citerne qui a fuit les 300 m³ a 5 boulons desserrés, des joints d’étanchéité largement distendus

 

Article lié : [Photo] On trouve déjà de la rouille dans l’intérieur des citernes à eau extrêmement radioactive

Le 20 septembre 2013, Tepco publie des photos de l’intérieur de la citerne qui a laissé fuir les 300 m³.

Leur brève inspection leur a fait découvrir que la citerne était déjà gravement détériorée.
Environ 1/3 de la plaque du fond avait perdu ses jointures d’étanchéité. Il y avait aussi 5 boulons desserrés.

↓ boulons desserrés

300m3 leakage tank had 5 loosened bolts, sealing parts widely detached

↓ Joint distendu

2 300m3 leakage tank had 5 loosened bolts, sealing parts widely detached

↓ Joints déformés

3 300m3 leakage tank had 5 loosened bolts, sealing parts widely detached

↓ Joints déformés

4 300m3 leakage tank had 5 loosened bolts, sealing parts widely detached

↓ Plaque latérale rouillée

5 300m3 leakage tank had 5 loosened bolts, sealing parts widely detached

http://www.tepco.co.jp/nu/fukushima-np/handouts/2013/images/handouts_130920_06-j.pdf
Vous pouvez ignorer la vérité mais la vérité ne vous ignorera pas.

About this site

This website updates the latest news about the Fukushima nuclear plant and also archives the past news from 2011. Because it's always updated and added live, articles, categories and the tags are not necessarily fitted in the latest format.
I am the writer of this website. About page remains in 2014. This is because my memory about 311 was clearer than now, 2023, and I think it can have a historical value. Now I'm living in Romania with 3 cats as an independent data scientist.
Actually, nothing has progressed in the plant since 2011. We still don't even know what is going on inside. They must keep cooling the crippled reactors by water, but additionally groundwater keeps flowing into the reactor buildings from the broken parts. This is why highly contaminated water is always produced more than it can circulate. Tepco is planning to officially discharge this water to the Pacific but Tritium is still remaining in it. They dilute this with seawater so that it is legally safe, but scientifically the same amount of radioactive tritium is contained. They say it is safe to discharge, but none of them have drunk it.