Murata ex JP ambassador, “Coolant system of reactor4 was broken 12/8~12/11, concrete base is terribly deteriorating.”
According to Mr. Murata, former Japanese ambassador in Switzerland, the coolant system of SFP of reactor4 was stopped from 12/8 to 12/11, and the concrete base is terribly damaged already.
[Leakage for 2 continuous days] 15m3 of contaminated water leaked in reactor3 turbine building
On 12/11/2012, 15m3 of contaminated water leaked again in reactor3 turbine building. The radioactive density in the leaked water was Cs-134 : 4.2E+7 Bq/m3 Cs-137 : 7.4E+7 Bq/m3 Related article..[Column]
The M7.4 of 12/7/2012 was actually 2 continuous different earthquakes
About the M7.4 of 12/7/2012, Earthquake Research Committee of the government announced it was two continuous earthquakes which are separated. According to the analysis of meteorological agency and Earthquake Research
Highly radioactive water leakage at desalination system of Fukushima plant, “4 mSv/h of beta ray on its surface”
Because “Header joint part came off due to the RO cassette drain valve was opened after being touched.”, highly contaminated water leaked from desalination system on 12/10/2012. It was 4mSv/h
[Mainichi] Saitama city builds temporary storage for radiation-contaminated soil
<Quote> [Mainichi] MISATO, Saitama — The municipal government here began building a temporary storage site in August for soil contaminated by radioactive materials released in the Fukushima No. 1 nuclear