Following up this article..Tepco to “improve” the ground to stop groundwater contamination spreading by crushing an observation hole [URL]
According to Tepco, they completed 16% of ground improvement on the east side of reactor 1 and 2 by the morning of 7/17/2013.
Due to this construction, the boring No.1-1 can no longer be used, which was the closest observation hole to the sea.
Tepco started the construction on 7/8/2013 with 8 ground improvement devices. They work from 19:00 to 7:00 everyday.
http://www.tepco.co.jp/nu/fukushima-np/handouts/2013/images/handouts_130717_08-j.pdf
http://photo.tepco.co.jp/date/2013/201307-j/130717-01j.html
Iori Mochizuki
Thank you for your support. Monthly donation is also very helpful !
_____
Français :
Tepco a avancé sur 16% de la stabilisation du sol du côté est des réacteurs 1 & 2
Article lié : Tepco va “renforcer” le sol pour arrêter la contamination souterraine en écrasant un trou d’observation
Selon Tepco, ils ont terminé à 16% la stabilisation du sol du côté Est des réacteurs 1 et 2 dans la matinée du 17 juillet 2013.
Le forage N° 1-1 ne peut plus être utilisé alors qu’il était le trou d’observation le plus près de la mer à cause de cette construction.
Tepco affirme avoir commencé le 8 juillet 2013 la construction de 8 dispositifs d’amélioration du sol. Ils travaillent de 19:00 à 7:00 toutes les nuits.
http://www.tepco.co.jp/nu/fukushima-np/handouts/2013/images/handouts_130717_08-j.pdf
http://photo.tepco.co.jp/date/2013/201307-j/130717-01j.html
Merci de votre soutien. Les virements mensuels sont aussi très utiles !