Tepco completed steel frame of reactor4 cover to start installing fuel removing crane

According to Tepco, they completed building the steel frame of reactor4 cover on 5/29/2013.

The construction was started on 1/8/2013.

In order to remove the fuel assemblies from SFP4, they are going to install the crane from early June.

Tepco completed steel frame of reactor4 cover to start installing fuel removing crane

 

2 Tepco completed steel frame of reactor4 cover to start installing fuel removing crane

 

http://www.tepco.co.jp/nu/fukushima-np/handouts/2013/images/handouts_130529_11-j.pdf

 

 

 

Thank you for your support.
Now your donation will be spent on the next research for the possibile Japanese village in Romania. (560€)
At this moment, 371 € to go.

_____

Français :

Tepco a terminé le cadre d’acier de couverture du réacteur 4 permettant de commencer la mise en place de la grue à retirer les combustibles

 

Selon Tepco, ils ont fini la construction du cadre en acier de couverture du réacteur 4 le 29 mai 2013.

Sa construction avait commencé le 8 janvier 2013.
Pour pouvoir retirer les assemblages de combustible de la SFP4 (piscine des barres de combustible usagées), ils doivent mettre en place une grue début juin.

Tepco completed steel frame of reactor4 cover to start installing fuel removing crane
2 Tepco completed steel frame of reactor4 cover to start installing fuel removing crane

http://www.tepco.co.jp/nu/fukushima-np/handouts/2013/images/handouts_130529_11-j.pdf

Merci pour votre aide.
Vos dons vont maintenant servir à la recherche suivante, Les possibilités de faire un village japonais en Roumanie. (560€)
En ce moment, il manque 371 €.

About Author