Tepco failed in shutting up retained water even with cement / Water level becomes back only within 2.5 hours

Photo : Injecting cement and grout to underground trench. Taken on 11/25/2014.    Following up this article.. Retained water underground temperature went up by 10℃ near Reactor 2 / Tepco

Breaking news Contaminated water crisis Cover-ups Fukushima Plant

Retained water underground temperature went up by 10℃ near Reactor 2 / Tepco “Still investigating the cause”

Following up this article.. Tepco to give up the preceding frozen wall and directly fill the trenches with cement instead [URL]   The retained water temperature went up by 10℃

Breaking news Cover-ups Fukushima Plant

Underground structure rapidly heated by up to 40℃ when water reduced

Underground trench water gets rapidly heated when water level decreases, according to Tepco.   On 10/3/2014, Tepco released the report about the failed frozen water wall project. (cf, Tepco to

Breaking news Contaminated water crisis Fukushima Plant

Tepco to give up the preceding frozen wall and directly fill the trenches with cement instead

Photo : Fukushima workers putting ice cubes to “frozen water” wall to make it frozen temporally. 7/24/2014.   Following up this article.. Tepco “Never give up the frozen wall project”

Breaking news Contaminated water crisis Fukushima Plant

Tepco “Never give up the frozen wall project”

Photo : Floating ice put into the underground trench. The camera catches the white noise due to the high level of radiation from contaminated water.    Following up this article..

Breaking news Contaminated water crisis Fukushima Plant

JP Gov to decide to abort the preceding “frozen water wall” project on 8/19/2014

NRA (Nuclear Regulation Authority) is going to decide to abort the frozen water wall project in underground trench on 8/19/2014. This is the frozen water wall  project followed by frozen

Breaking news Contaminated water crisis Fukushima Plant

Drain pipes got clogged due to dry ice project for frozen water wall

Dry ice ended up clogging the drain pipes, according to Tepco. In order to freeze the unfreezable frozen wall, Tepco has been putting ice and dry ice into the underground

Breaking news Contaminated water crisis Fukushima Plant

Desperate Tepco to drop ice and dry ice to help “frozen wall” be frozen

Following up this article..   Preceding “frozen” water wall not frozen over 2 months – Video [URL]   On 7/7/2014, Tepco admitted the preceding “frozen” water wall hasn’t gotten frozen

Contaminated water crisis Fukushima Plant

Preceding “frozen” water wall not frozen over 2 months – Video

Following up this article..   Preceding frozen water wall hasn’t worked since April [URL]   Related to this article.. Fukushima worker “Frozen wall was originally designed to stand with clay

Contaminated water crisis Cover-ups Plant hazard

2,200,000,000,000 Bq/m3 of All β was measured seaside trench of Reactor2 last year/ Tepco underrated 1/3× for a year